Procurement & Logistics
Buying the equipment is only part of the job. Coordinating approvals, lead times, manufacturing, and delivery in the right sequence is what keeps procurement aligned with construction.

SIVAT Water Solutions manages procurement and logistics for aquatic equipment packages: purchase orders, submittal approvals, manufacturer lead times, production releases, freight and delivery sequencing aligned to the construction schedule.
What we manage
Manufacturer coordination. Specialty aquatic equipment comes from a fragmented supplier base. One package can involve a dozen manufacturers with different lead times, different submittal requirements, and different shipping arrangements. We hold that together.
Lead-time management. Long-lead items on aquatic projects are frequently not the ones people expect. Custom FRP vessels, large filter tanks, and specialty control panels can outrun the pumps and valves by months. Identifying which items drive the schedule needs to happen at buyout, not at the first delivery meeting.
Equipment scheduling and delivery sequencing. Material arriving too early costs storage and double handling. Arriving too late costs everything else. Sequencing follows the installation schedule.
Procurement coordination. Purchase orders, expediting, order status, and change management across the package.
Where this shows up on the bid
Lead times checked before the number goes into the bid can materially change what an estimator can commit to. A contractor who understands the timing for long-lead FRP, controls, filtration, and other specialty equipment can build the schedule around it instead of discovering the constraint after award.
We confirm availability during the bid phase, not after award.
A note on availability
Equipment is superseded, discontinued, and re-engineered over time. A schedule written months earlier may specify a model that is no longer available or no longer the best fit. We flag those issues during the bid and, where appropriate, propose an equal or better alternative through the project’s formal review process.
Common questions
What are typical lead times for aquatic life support equipment?
Lead times vary by category and manufacturer. Standard pumps, valves and strainers are typically stocked or built in weeks. Engineered items such as large filters, FRP vessels, ozone systems, heat exchangers and control panels are built to order and can take several months. SIVAT checks current lead times during the bid so the schedule is protected before the number is submitted.
Who manages submittals and approvals before equipment is released for production?
SIVAT prepares the submittal package, tracks it through the engineer’s review, and does not release engineered equipment for production until it is approved. Equipment built to an unapproved submittal is the most expensive item on the project to correct.
How does SIVAT sequence deliveries?
We schedule production releases and freight against the construction sequence so equipment arrives when the room and the trades are ready for it. Early deliveries create storage and double handling; late deliveries hold up installation and commissioning. Where possible, we proactively track upcoming manufacturer price increases and give customers advance notice, helping them decide whether to release equipment early and lock in current pricing before new pricing takes effect.
Support across the project